单项选择题
Company.com is migrating from a third party managed disk subsystem to an IBM TotalStorage Enterprise Storage Server. Connection of the new storage server is complete, and it has been tested on all of the nodes in the three node HACMP cluster.
How does the customer migrate to the new storage server with minimum down time?()
A. Shut down one node at a time and let the other node serve the application
B. Stop HACMP with the forced option and perform migration of the disks on one node,then restart HACMP
C. Stop both nodes and perform the migration all at once using standard AIX commands in parallel, then restart the cluster
D. Use C-SPOC to add the new disks to the cluster and migrate the information off the existing disks, then remove the old disks with C-SPOC
相关考题
-
单项选择题
Company.comwithanEtherChannelimplementationisconsideringanHACMPsolution.Whatconsiderationsmustbeaddressedinplanningthisconfiguration?()
A. Hardware address takeover must be configured.
B. IPAT via IP aliasing is required for EtherChannel.
C. EtherChannel must be defined as a separate network.
D. HACMP does not support the fallover of EtherChannel. -
单项选择题
Continuous availability is required for an application in a two-node cluster. There is one rotating resource group in the cluster, and the nodes are identical machines. Client telnet connections to the application cannot be broken because it takes 20 to 30 minutes to recycle the client workstations and transactions will be lost. What configuration best provides continuous connectivity to the application?()
A. IPAT using IP Replacement without MAC address takeover.
B. IPAT using IP Aliasing and hardware MAC address takeover.
C. None because continuous telnet connectivity cannot be provided with HACMP.
D. Shared service IP address assigned to multiple network interface cards on each node. -
单项选择题
Company.com wishes to use IPAT via IP replacement in a two-node mutual cluster. Each node has two Ethernet 10/100/1000 adapters. Throughout the planning session,the customer has asked questions about subnet and VLAN requirements for the intended network topology. Which of the following best describes the network requirements?()
A. The service IP addresses must be on a separate subnet and VLAN.
B. The non-service and service IP addresses must be on the same subnet and on the same VLAN.
C. All interfaces on a node must be in different subnets. All subnets must be on the same VLAN.
D. One non-service and one service IP address must be on the same logical subnet. All interfaces must be on the same VLAN.