A customer’s data center has all POWER4+ systems, and they plan to add three new p5-570 systems.  They will be purchasing a new 7310-CR2 HMC to support the POWER5 systems.  What is a key requirement that they need to plan for with the new HMC?()

    A.A desk, as it not rack mountable
    B.Ethernet connections to the POWER5 systems
    C.Serial connections to the POWER5 systems
    D.USB connections for the keyboard and mouse